PP O’Connor completes major demolition works at St Peter’s Square, Manchester

PP O’Connor have safely and systematically demolished four multi-storey office buildings at St Peter’s Square in the heart of central Manchester.  Century, Bennett, Sussex and Clarendon Houses have been removed to prepare way for the No.2 St Peter’s Square, a new 11 storey building comprising 161,113 sq ft of office space and 5,142 sq ft of ground floor leisure space.

PP O’Connor was appointed by construction and engineering company Laing O’Rourke who has been hired by Mosley Street Ventures (the developers of No 2 St Peter’s Sqaure), which is headed by Fred and Peter Done.

Charmaine O’Connor, chief executive, PP O’Connor said:  “The demolition of four buildings in the heart of the city centre is not without its challenges, we’ve worked closely with our client Laing O’Rourke, and MPT (who are building the new Metrolink tram stop at St Peter’s Square directly opposite our site) to minimise the impact and disruption caused by the works. 

“We delivered the project on time and on budget, with all of the materials excavated or removed either being recycled back into in the final building or used elsewhere.  I look forward to seeing the completed No 2 St Peter’s Square in 2017.”

With a project value of approximately £600,000 the scope of operation included: the removal of all remaining loose furniture; soft strip of internal features; complex building separation from the remaining development within the block ahead of the hard demolition activities.

The demolition work also included the removal of ground floor slabs on two of the blocks.  The remaining two buildings have basements and PP O’Connor developed a temporary works solution to retain the existing basement walls during the demolition works and facilitate the piling operations when the construction of the new building begins.

The work was carried out in the full gaze of the general public, many of whom passed the time watching the work progress as they waited for trams in St Peter’s Square.

Demolition rubble from the superstructure was taken from site to PP O’Connor’s local recycling facility and crushed so that it could be returned to site to create the piling platforms to the new basement area of No. 2 St Peter’s Square.  Metal removed from the site has been recycled.PPO_Connor_St_PetersSQ02 (1280x720)